Image001Progress Labs at Progress Way in Gaithersburg, MD is a two-building approximately 495,000 SF development situated on 44 acres with I-270 visibility and access off of exit 11 Montgomery Village Avenue. Construction commenced at Progress Labs at 700 N. Frederick Avenue in Gaithersburg, MD back in October, and according to the video below (posted by Progress Labs on Monday, July 18th), is scheduled to be delivered in Q4 of 2022, which is ahead of schedule based on the schedule provided on its website, also seen below:

Building 1 Early TI Start: 11/2022

Building 2 Early TI Start: 2/2023

Building 1 Base Building Substantial Completion: 1/2023

Building 2 Base Building Substantial Completion: 4/2023

Click here to read more.

Leave a Reply

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

BioHealth Innovation will use the information you provide on this form to be in touch with you and to provide updates and marketing.